Frequently Asked Questions

Frequently Asked Questions

  • Should customs duties be paid for import/export of electricity in/from the Republic of Serbia?
  • Do I have to pay for the transit of electricity through the transmission network of the Republic of Serbia? How can I book the transmission capacity on interconnected power lines in the Republic of Serbia?
  • Under Article 10.1.3 of the “Rules on Cross-border Transmission Capacity Allocation of the public enterprise for electricity transmission and transmission system management „Elektromreza Srbije“ (PE EMS) for PE EMS control area borders for the period 01/01 – 31/01/2012”, curtailment might take place "due to the scheduled annual disconnections of the cross-border interconnection lines for regular maintenance, due to Force Majeure or other unplanned/unforeseen events in the electric power system." This notion of "unplanned/unforeseen events” is not defined in the rules and could cover a broader category of events for which curtailment might be possible, and there is a risk that it might go beyond the "emergency situations where the transmission system operator must act in an expeditious manner and re-dispatching or countertrading is not possible" which are in fact the only possibility for curtailment allowed by the Regulation 1228/2003 (Article 6(2)). Please clarify the notion of "unplanned/unforeseen or unscheduled events" (other than Force Majeure) in Articles 10.1.3, 10.1.7 and 10.2.3 of the Allocation Rules for 2012.
  • Article 10.1.8 of the “Rules on Cross-border Transmission Capacity Allocation of the public enterprise for electricity transmission and transmission system management „Elektromreza Srbije“ (PE EMS) for PE EMS control area borders for the period 01/01 – 31/01/2012” provides for a definition of Force Majeure by stipulating that "Force Majeure events and circumstances are those which could not be foreseen, prevented, avoided or eliminated by the measures undertaken to preserve safe and reliable operation of the electric power system, compliant with the Grid Code and which took place after the Allocation Procedure and in particular natural disasters, fires, flood, earthquakes, state of emergency and warlike operations as well as the measures of the state authorities and organizations of the transmission system operators." This definition of Force Majeure includes "measures of the state authorities and organizations of the transmission system operators", which would seem to constitute rather the reactions to an emergency situation than the emergency situation itself. Please specify which measures of the state authorities and organizations of the transmission system operators in Article 10.1.8 of the Allocation Rules for 2012 could be considered Force Majeure. Please clarify if only measures required as an expeditious reaction to emergency situations can trigger capacity curtailment.
News
Decisions of the Council of the Energy Agency of the Republic of Serbia

Upon the request of “Elektromreža Srbije” JSC Belgrade and “Elektrodistribucija Srbije” LLC Belgrade, at its session held on August 21, 2025, the Council of the Energy Agency of the Republic of Serbia has granted approval for the decisions on the electricity transmission and distribution tariffs, which will apply starting from October 1, 2025.

The total approved transmission tariff increase in 2025, compared to the approved tariff as of October 1, 2021, amounts to 10%, while the total approved electricity distribution tariff increase, compared to the approved price as of October 1, 2021, calculated based on the 2025 balance, amounts to 16%.


AERS: Decision on the Electricity Price for Guaranteed Supply

Upon the request of “Elektroprivreda Srbije” JSC Belgrade, at its session held on August 28, 2025, the Council of the Energy Agency of the Republic of Serbia has granted approval for the decision on the electricity guaranteed supply price, which will be applied starting from October 1, 2025.

The average electricity price for customers entitled to guaranteed supply at regulated prices (households and small customers) is higher than the current average price by 6.6%, due to the increase in transmission and distribution tariffs.


AERS: Joint Natural Gas Transmission Tariffs

Belgrade, July 11, 2025

On the session held on July 11, 2025, the Council of the Energy Agency of the Republic of Serbia has adopted a Decision on Joint Natural Gas Transmission Tariffs. In accordance with the Methodology for Setting Natural Gas Transmission Tariffs, this decision establishes joint natural gas transmission tariffs considered as a whole, which are applied by “Transportgas Srbija” d.o.o. Novi Sad and “Yugorosgaz-Transport” d.o.o. Niš during the first regulatory period lasting three gas years — from October 1, 2025, to September 30, 2028.


Approval of the Natural Gas Distribution System Development Plan of the Distribution System Operator “GAS” d.o.o. Bečej

Belgrade, July 11, 2025

On the session held on July 11, 2025, the Council of the Energy Agency of the Republic of Serbia has adopted a decision granting approval to the Distribution System Development Plan for the period 2025–2029, along with the Investment Plan for the period 2025–2027, submitted to the Agency by the natural gas distribution system operator “GAS” d.o.o. Bečej.


PUBLIC CONSULTATION: Draft Transmission System Development Plan of the Republic of Serbia for the Period 2025–2034

Belgrade,  June 19, 2025

On June 19, 2025, the Energy Agency of the Republic of Serbia has launched a public consultation on the Draft Transmission System Development Plan of the Republic of Serbia for the period 2025–2034, submitted to the Agency by the transmission system operator “Elektromreža Srbije” a.d.


Instructions for working with clients